Line performance test for new filling and packaging lines

A practical checklist for agreeing and running a performance or OEE acceptance test on a new food, dairy or beverage line: rate, exclusions, test window, data source and sign-off.

Publisher: Liquid Consulting. Free to adapt with attribution to Liquid Consulting.

Buying a new filling or packaging line usually comes with an output or OEE guarantee. The guarantee only holds if the figure, the test and the data are agreed before signing. This page is Liquid’s general checklist for doing that. Project-specific contract terms always win when they exist.

It sits beside the Commissioning kickoff and close pack, whose item 3.4 is the performance test step. For the rest of the acceptance path, see commissioning, FAT and SAT.

1. What a performance test proves (and what FAT/SAT does not)

Factory and site acceptance testing show that the equipment and its PLC, HMI and SCADA control are built and working as specified. They do not show that the line sustains an agreed rate over a full run with real product, real packaging material and normal crews. The performance test does.

  • [ ] Everyone agrees the performance test is a separate step from FAT and SAT
  • [ ] The test is written into the contract or the commissioning plan, not left to be arranged later
  • [ ] FAT and SAT are signed off before the performance test starts

2. Agree before signing

Most disputes come from something nobody wrote down. Settle these points in writing while the buyer still has leverage.

  • [ ] The guaranteed figure, and exactly how it is calculated (output or OEE, and over what period)
  • [ ] The ideal (nameplate) rate the figure is measured against, per product and pack format
  • [ ] Which stops are excluded from the figure, and which are not
  • [ ] Test duration: [blank] hours or shifts
  • [ ] Products and pack formats included in the test
  • [ ] Who supplies operators, product, packaging material and utilities during the test
  • [ ] Who may adjust the line during the test, and how adjustments are recorded
  • [ ] What happens if the test is interrupted for reasons outside the line

3. The data source

A guarantee is only as good as the numbers behind it. Decide where counts, stops and rejects come from before the test, not when the results are disputed.

  • [ ] One named source for good count, reject count and stop reasons (PLC and HMI counters, or the line data system)
  • [ ] Counters and stop codes checked and signed off before the test starts
  • [ ] All data time-stamped from a single agreed clock
  • [ ] Manual counts and operator notes recorded alongside, as a cross-check
  • [ ] Raw data exported in an agreed format, readable by both buyer and supplier
  • [ ] Named owner of the raw data during the test; nobody edits it
  • [ ] Where the raw data is stored after the test, and for how long

4. Running the test

Pre-test checks

  • [ ] FAT and SAT items closed, or open items agreed in writing as not affecting the test
  • [ ] Line cleaned and set up for the first agreed product and pack format
  • [ ] Operators trained and the test crew named
  • [ ] Product, packaging material and utilities on hand for the full window
  • [ ] Data capture running and verified against a short manual count

The test window

  • [ ] Start time and end time recorded and signed by both sides
  • [ ] Every stop logged with a time, a reason and who caused it
  • [ ] Deviations from the agreed conditions recorded as they happen

What pauses the clock and what does not

Agree this list before the test. A stop caused by something the buyer supplies, such as missing material or no operator, is often paused. A stop caused by the line itself, its controls or its upstream and downstream equipment from the same supplier normally is not. Whatever the parties decide, write it down and apply it the same way for every stop.

  • [ ] Pause rules written down and signed before the start
  • [ ] Each pause logged with a start time, an end time and the rule applied

5. When the line misses

A missed figure is not the end of the agreement. It starts the corrective plan, which should already be written into the contract.

  • [ ] Results documented against the agreed figure, with the raw data attached
  • [ ] Causes identified from the stop log, with an owner for each
  • [ ] Corrective plan with owners and dates
  • [ ] Re-test terms agreed: what is repeated, for how long, and who bears the cost
  • [ ] What the buyer may do if the line still misses after the re-test
  • [ ] Final results, deviations and sign-off filed with the commissioning documentation

6. One-page line performance test checklist (print this)

Before signing

  • [ ] Guaranteed figure and how it is calculated
  • [ ] Ideal (nameplate) rate per product and pack format
  • [ ] Excluded stops listed
  • [ ] Test duration [blank], products and pack formats
  • [ ] Operators, product and materials: who supplies what

Data

  • [ ] One named, time-stamped data source
  • [ ] Counters and stop codes verified
  • [ ] Raw data owner named; no edits during the test

Before the test

  • [ ] FAT and SAT signed off
  • [ ] Line set up, crew trained, materials on hand
  • [ ] Data capture checked against a manual count

During the test

  • [ ] Start and end signed by both sides
  • [ ] Every stop logged with reason and cause
  • [ ] Pause rules applied the same way each time

After the test

  • [ ] Results against the agreed figure
  • [ ] Corrective plan and re-test terms if missed
  • [ ] Raw data and sign-off filed

This checklist does not replace the contract, site safety rules, permits or lockout procedures. Questions: contact.us@liquidconsulting.com

7. Common
Questions

What is a line performance test?

A line performance test is a planned run, after commissioning, in which a new line is operated against figures agreed in writing before signing. It proves the line delivers the guaranteed output or OEE under stated conditions. FAT and SAT prove it is built and working; the performance test proves it performs.

What should be excluded from an OEE guarantee?

Whatever the parties agree in writing before the test, and nothing more. Typical candidates are planned stops, waiting for materials or operators supplied by the buyer, and changeovers outside the agreed formats. Everything not listed as excluded counts against the figure.

How long should a performance test run?

Long enough to cover the agreed product and pack formats and normal shift patterns, not just a good hour. Write the duration into the agreement as [blank] hours or shifts, and say what pauses the clock and what does not.

Who should own the test data?

Agree it before the test. The usual approach is that counts, stops and rejects come from one time-stamped source, such as the PLC and HMI counters or the line data system, and both buyer and supplier can read the raw data throughout. Nobody edits it during the test.

More Free Field Resources

Browse the resources hub for related templates and training guides.

Talk To An
Automation Engineer

Tell us what you run and how it is reached today. You will speak with an automation engineer, not a sales rep. We respond within one business day.

If you are not ready to talk Work through the self-check list. It costs nothing and it will tell you whether you have a problem.