Buying a new filling or packaging line usually comes with an output or OEE guarantee. The guarantee only holds if the figure, the test and the data are agreed before signing. This page is Liquid’s general checklist for doing that. Project-specific contract terms always win when they exist.
It sits beside the Commissioning kickoff and close pack, whose item 3.4 is the performance test step. For the rest of the acceptance path, see commissioning, FAT and SAT.
1. What a performance test proves (and what FAT/SAT does not)
Factory and site acceptance testing show that the equipment and its PLC, HMI and SCADA control are built and working as specified. They do not show that the line sustains an agreed rate over a full run with real product, real packaging material and normal crews. The performance test does.
- [ ] Everyone agrees the performance test is a separate step from FAT and SAT
- [ ] The test is written into the contract or the commissioning plan, not left to be arranged later
- [ ] FAT and SAT are signed off before the performance test starts
2. Agree before signing
Most disputes come from something nobody wrote down. Settle these points in writing while the buyer still has leverage.
- [ ] The guaranteed figure, and exactly how it is calculated (output or OEE, and over what period)
- [ ] The ideal (nameplate) rate the figure is measured against, per product and pack format
- [ ] Which stops are excluded from the figure, and which are not
- [ ] Test duration: [blank] hours or shifts
- [ ] Products and pack formats included in the test
- [ ] Who supplies operators, product, packaging material and utilities during the test
- [ ] Who may adjust the line during the test, and how adjustments are recorded
- [ ] What happens if the test is interrupted for reasons outside the line
3. The data source
A guarantee is only as good as the numbers behind it. Decide where counts, stops and rejects come from before the test, not when the results are disputed.
- [ ] One named source for good count, reject count and stop reasons (PLC and HMI counters, or the line data system)
- [ ] Counters and stop codes checked and signed off before the test starts
- [ ] All data time-stamped from a single agreed clock
- [ ] Manual counts and operator notes recorded alongside, as a cross-check
- [ ] Raw data exported in an agreed format, readable by both buyer and supplier
- [ ] Named owner of the raw data during the test; nobody edits it
- [ ] Where the raw data is stored after the test, and for how long
4. Running the test
Pre-test checks
- [ ] FAT and SAT items closed, or open items agreed in writing as not affecting the test
- [ ] Line cleaned and set up for the first agreed product and pack format
- [ ] Operators trained and the test crew named
- [ ] Product, packaging material and utilities on hand for the full window
- [ ] Data capture running and verified against a short manual count
The test window
- [ ] Start time and end time recorded and signed by both sides
- [ ] Every stop logged with a time, a reason and who caused it
- [ ] Deviations from the agreed conditions recorded as they happen
What pauses the clock and what does not
Agree this list before the test. A stop caused by something the buyer supplies, such as missing material or no operator, is often paused. A stop caused by the line itself, its controls or its upstream and downstream equipment from the same supplier normally is not. Whatever the parties decide, write it down and apply it the same way for every stop.
- [ ] Pause rules written down and signed before the start
- [ ] Each pause logged with a start time, an end time and the rule applied
5. When the line misses
A missed figure is not the end of the agreement. It starts the corrective plan, which should already be written into the contract.
- [ ] Results documented against the agreed figure, with the raw data attached
- [ ] Causes identified from the stop log, with an owner for each
- [ ] Corrective plan with owners and dates
- [ ] Re-test terms agreed: what is repeated, for how long, and who bears the cost
- [ ] What the buyer may do if the line still misses after the re-test
- [ ] Final results, deviations and sign-off filed with the commissioning documentation
6. One-page line performance test checklist (print this)
Before signing
- [ ] Guaranteed figure and how it is calculated
- [ ] Ideal (nameplate) rate per product and pack format
- [ ] Excluded stops listed
- [ ] Test duration [blank], products and pack formats
- [ ] Operators, product and materials: who supplies what
Data
- [ ] One named, time-stamped data source
- [ ] Counters and stop codes verified
- [ ] Raw data owner named; no edits during the test
Before the test
- [ ] FAT and SAT signed off
- [ ] Line set up, crew trained, materials on hand
- [ ] Data capture checked against a manual count
During the test
- [ ] Start and end signed by both sides
- [ ] Every stop logged with reason and cause
- [ ] Pause rules applied the same way each time
After the test
- [ ] Results against the agreed figure
- [ ] Corrective plan and re-test terms if missed
- [ ] Raw data and sign-off filed
Related Liquid resources
- Commissioning kickoff and close pack
- Commissioning, FAT and SAT
- Food and beverage automation
- Automation assessment
- Training
This checklist does not replace the contract, site safety rules, permits or lockout procedures. Questions: contact.us@liquidconsulting.com