This pack is Liquid’s general commissioning workflow. It is meant to work across systems. Project-specific test schedules still win when they exist. Sequence can shift with customer planning; the ambition is to cover every step deliberately rather than skip quietly.
Commissioning here means testing installed (or nearly complete) equipment, a facility area, or a plant so it meets its design objectives. In practice, “commissioning proper” often starts at the first water tests. Everything before that is readiness.
Pair this pack with Documenting a mission and the blank **Field work report** template.
1. Kickoff: initial start-up meeting
Hold this first. Prefer booking it before travel. Introduce the crew, exchange contacts, and walk the workflow below so the customer sees how you will work.
Kickoff agenda
- [ ] Who is the project lead?
- [ ] What was ordered?
- [ ] Who is involved on site (customer and Liquid)?
- [ ] Time schedule and milestones
- [ ] When is equipment access available?
- [ ] What is the expected result / success criteria?
- [ ] Extra material, tools, media, or people needed now?
- [ ] Site safety, permits, and stop-work rules (follow the site)
- [ ] How daily reports and the weekly field work report will be shared
- [ ] Agree the content of the mission; write down extra customer requests
Put minutes in the first daily log and the field work report. Escalate urgent disagreements the same day.
Kickoff minutes (fill in)
2. Control points before commissioning starts
Do not call the job “in commissioning” until readiness is honest. Work through the list; adapt wording to the line you are on.
Documentation and software
- [ ] Equipment technical manuals available
- [ ] Electrical manuals available
- [ ] Operator manuals available
- [ ] Flowcharts / P&IDs available
- [ ] Workshop or factory test report available (if applicable)
- [ ] Automation programs available for the installed revision
- [ ] Commissioning kit and recommended spare parts available (from the equipment bill of materials)
Installation and media
- [ ] Modules or skids installed and interconnected as required for the production line
- [ ] Media supply matches installation data (pressure, capacity, quality)
- [ ] Electrical supply ready
- [ ] Instrument air ready
- [ ] Steam ready (if used)
- [ ] Water ready (cold, tower, chilled / ice water as required)
Component and identity checks
- [ ] Machine identification plate present and readable
- [ ] Warning signs present
- [ ] Module components present per flowchart and item list
- [ ] Line components outside modules present per flowchart
Electrical panel (before and as you energize carefully)
- [ ] Main power to the panel verified before switching in
- [ ] Control power to instruments and PLC verified
- [ ] Emergency stop function checked
- [ ] Actual program loaded in PLC and on the operator panel / HMI
- [ ] Communication to other modules verified (hardware and software)
I/O check
- [ ] Valves (digital and analogue outputs) proven
- [ ] Pumps: rotation checked; frequency converters set
- [ ] Transmitters and instruments: power and parameter settings checked
First water in
- [ ] Media lines flushed to drain before opening into the equipment (water, steam, air as applicable)
- [ ] Equipment filled with water carefully (manual activation of product pump and valves as needed)
- [ ] Levels checked and adjusted on balance tanks, deaerators, flash or infusion vessels, and other process vessels
3. Commissioning steps
If a specific test schedule exists for this equipment, follow it. Otherwise use this sequence.
3.1 Water test
Prove flows, levels, interlocks, and basic sequences on water before product.
- [ ] Test plan agreed
- [ ] Results, issues, and fixes recorded in the field work report
- [ ] Open items owned
3.2 CIP test
Prove cleaning sequences and local adaptations. Record concentrations, temperatures, times, and deviations. Do not invent OEM chemical recipes here; use the project’s approved chemicals and methods.
- [ ] CIP test plan agreed
- [ ] Results recorded
- [ ] Deviations and local adaptations noted
3.3 Product test
Run with the actual product that normal production will use.
- [ ] Product available and approved for trial
- [ ] Volumes, start/stop, alarms, and deviations recorded
- [ ] Parameter list updated (detailed numbers live there; the FWR carries the narrative)
3.4 Performance test
Sterility, pasteurization, or other criteria defined by the project.
- [ ] Acceptance criteria clear before the test
- [ ] Results documented against those criteria
- [ ] Failures have a corrective plan
Optional steps often done with commissioning
- [ ] Operator and maintenance training
- [ ] Production supervision after release
- [ ] Help set up a preventive maintenance schedule
4. Document results while you are still on site
- [ ] Update changes in technical, electrical, and operator manuals and in flowcharts
- [ ] Update automation programs and take verified backups
- [ ] Finalize the field work report (summary answers why, done?, findings, remaining, agreements, recommendations)
- [ ] File performance-test evidence
- [ ] Upload backups and reports to the Liquid team site
- [ ] Remove temporary PLC / HMI settings and trace tags before the final backup
5. Close: final wrap-up meeting
Hold this before you leave site. The goal is shared truth: done or not, what remains, who owns it, and how the customer feels about the visit.
Wrap-up agenda
- [ ] Short summary of what was done
- [ ] Agree whether the mission is finalized
- [ ] Remaining items
- [ ] How and when remaining items will be solved
- [ ] Customer feedback and extra requests
- [ ] Next visit or support plan (if any)
Put minutes in the last daily log and in the field work report summary.
Wrap-up minutes (fill in)
6. One-page commissioning checklist (print this)
Before start
- [ ] Kickoff meeting done and minuted
- [ ] Docs, programs, spares, media, install, panel, I/O, flush, first fill done
Execute
- [ ] Water test
- [ ] CIP test
- [ ] Product test
- [ ] Performance test
- [ ] Training / supervision / PM setup as agreed
Close
- [ ] Manuals and programs updated; backups stored
- [ ] Field work report finished
- [ ] Wrap-up meeting done and minuted
- [ ] Open items have owners and dates
- [ ] Site left in the agreed state
Related Liquid resources
This pack does not replace site safety rules, permits, or lockout procedures. Questions: contact.us@liquidconsulting.com