Planned service on aseptic process and filling equipment is usually split into lighter, more frequent minor service and deeper, less frequent major service. The equipment supplier’s recommendations and your plant’s quality system set the baseline. This page is Liquid’s general method for deciding what each service should actually include, based on the condition and history of your equipment.
Record the as-found and as-left condition with the Field work report template.
1. What minor and major service mean
- Minor service: planned inspection, adjustment and replacement of items found worn, done in a short planned stop without taking critical assemblies apart
- Major service: planned teardown and inspection of critical assemblies, including the components that keep the product zone sterile, followed by the verification your quality system requires before production restarts
Both are planned. The difference is depth, the stop they need, and what has to be verified afterwards.
2. Why the calendar alone is not enough
Two identical machines can wear very differently. Product, running time, cleaning and sterilization programs, water quality and operating conditions all change how fast parts wear. A scope based only on the calendar replaces some parts that are still good and can miss others that are failing.
- [ ] The supplier’s recommendations are the starting point, not the whole scope
- [ ] Your own condition and history data adjust the scope for your line
- [ ] Changes to the baseline go through the plant’s change control
3. Scope from condition
Collect what the line is telling you before deciding the scope.
- [ ] Findings recorded at the last service: what was worn, what was close
- [ ] Operator and maintenance observations since then: leaks, noises, sticking, drift
- [ ] Alarm and stop history from the PLC and HMI, grouped by assembly
- [ ] Deviations in sterilization, cleaning or CIP records
- [ ] Hygiene and leak test findings
- [ ] Trends in recorded temperatures, pressures or other measurements, where available
4. Scope from history
- [ ] Maintenance history for each assembly: what was replaced, and what was found
- [ ] Recurring failures and the fixes that did or did not last
- [ ] Changes since the last service: products, recipes, cleaning programs, running pattern
- [ ] Open actions from earlier services that were deferred
5. Build the scope
Go through the equipment assembly by assembly and decide one action for each, with the reason written next to it.
- Inspect: condition unknown or borderline; look and record
- Replace: condition or history says it will not last until the next planned service
- Overhaul: the assembly needs to come apart to be judged or restored
- Defer: condition and history support leaving it, with the reason recorded
Rank the work by risk: product safety and sterility first, then people’s safety, then output. Anything that affects the sterile barrier is not deferred without the approval your quality system requires.
6. Prepare and carry out the service
- [ ] Spares and consumables for the scope confirmed before the stop
- [ ] Procedures and work instructions available for each task
- [ ] People qualified for the tasks they will do
- [ ] Permits, isolation and lockout planned
- [ ] As-found and as-left condition recorded for every assembly worked on
7. After the service
- [ ] Verification and release steps your quality system requires, completed and signed
- [ ] Maintenance history updated with what was found, not just what was replaced
- [ ] Deferred items listed with owners for the next service
- [ ] Findings fed back into the scope for the next service
8. One-page scoping checklist (print this)
- [ ] Supplier recommendations and plant baseline at hand
- [ ] Last service findings reviewed
- [ ] Alarm, stop and deviation history reviewed
- [ ] Changes since the last service listed
- [ ] Inspect, replace, overhaul or defer decided per assembly, with reasons
- [ ] Work ranked by sterility, safety and output risk
- [ ] Spares, procedures, people and permits confirmed
- [ ] As-found and as-left recorded; history updated